A two-country platform across Thailand and Malaysia with secured utility power, verified land, and defined delivery programmes.
450 MW
Secured Capacity
330 MW
December 2027
2.0+ GW
Development Roadmap
Delivery Program
TH-01 · MY-01 · TH-03 · TH-02 — secured positions with defined delivery programmes
Secured Expansion
Indonesia 700 MW · Bosnia 100 MW
Prospective
Italy 100 MW · Greece 75 MW — under evaluation

Pathum Thani, Thailand
mw
50 MW → 130 MW IT
rfs
~Q1 2028 (Phase I)
density
600 kW/rack
gpu
NVL576 · GB300-Ready
cooling
100% Liquid
tenure
BOI Freehold
Power & Grid
PEA 115/22 kV dual-circuit via Bang Pa-In & Sam Khok · 50 MW confirmed (PEA letter May 2026) · NNEG cogeneration backup (185–199 MW installed, island-mode N+2)
RFS
~Q1 2028
RFS
~Q1 2029

Seremban, Malaysia
mw
45 MW → 160 MW IT
rfs
~May 2027 (9-month build)
density
142 kW/rack
gpu
GB300 NVL72
cooling
Liquid-Cooled
tenure
99-Year Leasehold
Power & Grid
Dual 33 kV utility (TNB) incoming, ~60 MVA/circuit · Self-built 33 kV substation with 3×30 MVA transformers (2+1 configuration) · N+1 containerized 11 kV diesel gensets · Uptime Tier III / TIA-942 Rated-3
RFS
~May 2027
RFS
Phased


Bang Pahan, Ayutthaya, Thailand
mw
50 MW → 100 MW IT
rfs
Phase I Q4 2027
density
600 kW/rack
gpu
NVL576 · Rubin Ultra
cooling
100% Direct-to-Chip
tenure
BOI / Long Lease
Power & Grid
PEA Ayutthaya 3 High-Voltage Substation · 130 MW allocated (150 MW available at substation) · 115 kV dedicated on-site substation to be built · 800 VDC distribution platform standard · Single-source PEA supply with dual-circuit resilience design.
RFS
Q4 2027
RFS
Q2 2028

Phetchaburi, Thailand
mw
50 MW Grid-Ready
rfs
~May 2028
density
AI Compute Block
gpu
Flexible Density
cooling
Solar + BESS + Grid
tenure
BOI Eligible
Power & Grid
230 kV grid tower on parcel · 50 MW grid-ready (PEA confirmed) · On-site substation to be built within 18-month programme. Co-located 80 MW solar PV + 20 MW BESS via separate SPV.
RFS
~May 2028
Indonesia
700 MW
Secured position · Development programme under preparation
Bosnia
100 MW
Secured position · Development programme under preparation
Italy
100 MW
Greece
75 MW
Prospective sites are under evaluation and form no part of the 450 MW secured portfolio. Detailed information on secured sites is available through the project data room.
Detailed utility documentation, technical design, SLDs, connectivity studies and commercial terms are available under NDA through the project data room.